Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted

Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted AmountBuild formsApril 1$10,000Pour foundationApril 1$50,000May 1$100,000Frame wallsMay 1$30,000June 1$30,000Remaining tasksJuly 1 and beyond$500,000
Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Text-

Title: Project Management 

Subtitle: https://opentextbc.ca/projectmanagement/ 

ISBN: 978-1-77420-013-1 

Authors: Adrienne Watt 

Publisher: BCcampus 

Publication Date: August 14, 2014 

Edition: 2nd Edition

Looking for a Similar Assignment? Our ENL Writers can help. Use the coupon code SAVE30 to get your first order at 30% off!